[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981280":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":21,"analysis":22},981280,709,2,"多选题","预制桩的施工方法主要有（ ）。 A.打入法 B.静压入法 C振动法 D.钻孔法",[11,14,16,19],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",false,{"key":20,"text":20,"correct":18},"D","AB","预制桩基主要施工方法主要分为打入法和静压入法。打入法一般用锤击或振动法下沉，施工噪声大，挤土效应对周边环境影响大，不宜在城市使用。当持力层上有坚硬夹层时，也不宜使用。静力压入法即利用无噪声的机械将预制桩打入持力层。适用于软弱土层，当存在厚度大于2m的中密以上砂夹层时不宜使用。",{"id":6,"name":24,"category":25,"favorite":26},"岩土专业知识","建筑工程",0]