[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981279":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981279,709,2,"多选题","沉管灌注桩的单打法施工，应遵守的规定有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","必须严格控制最后30s的电流、电压值，其值按设计要求或根据试桩和当地经验确定",true,{"key":16,"text":17,"correct":14},"B","桩管内灌满混凝土后，先振动5?10s，再开始拔管，应边振边拔，每拔0.5?1.0m 停拔振动5 ~ 10s",{"key":19,"text":20,"correct":21},"C","在一般土层内，拔管速度宜在1.2~1.5m\u002Fmin 用活瓣桩尖时宜快，用预制桩尖时可适当减慢",false,{"key":23,"text":24,"correct":14},"D","在软弱土层中，拔管速度宜控制在0.6~0.8m\u002Fmin","ABD","根据《建筑桩基技术规范》（ JGJ 94—2008）第6. 5. 8条，单打法施工，应注意：①预制桩尖的位置应与设计相符，桩管应垂直套入桩尖，桩管与桩尖接触处应加垫草绳或麻绳；②沉桩过程中应经常探测管内有无地下水或泥浆；③必须严格控制最后30s的电流、电压值，其值按设计要求或根据试桩和当地经验确定；④管内灌满混凝土后先振动5 ~ 10s，再开始拔管，应边振边拔，每拔0.5~1m,停拔振动5~10s,如此反复，直至桩管全部拔出；⑤在一般土层中，拔管速度应控制在1.2?1.5m\u002Fmin，在软弱土层中宜控制在0.6?0.8mAnin，用活瓣桩尖时宜慢，用预制桩尖时可适当加快；⑥有钢筋笼时，混凝土的塌落度宜采用80 ~ 100mm，素混凝土桩宜采用60 ~ 80mm。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]