[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981270":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981270,709,2,"多选题","可能承受拔力的桩基有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","岸边工程桩基",true,{"key":16,"text":17,"correct":18},"B","季节性冻土地区桩基",false,{"key":20,"text":21,"correct":14},"C","膨胀土地区桩基",{"key":23,"text":24,"correct":18},"D","软土地区桩基","AC","在电力、石油、通信、交通设施及高层建筑中，往往采用桩基以承受较大的上拔荷载，典型的结构物有：①地下建筑物，诸如地下车库、飞机库、地下室、船坞、泵房、船闸等，在这些构筑物下设置的桩，往往承受较大的浮托力；②承受巨大水平荷载的叉桩结构，如码头、桥台、挡土墙下的斜桩；③塔式结构物，包括电视塔、通信塔、 高层建筑等高耸结构物桩基、高压输电线路杆塔基础、海洋平台桩基等；④特殊地区建筑物，如地震荷载作用下的桩基和膨胀土及冻胀土上的建筑桩基。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]