[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981268":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981268,709,2,"多选题","对于可能出现负摩阻力的桩基，宜按下列原则进行设计，其中正确的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对位于中性点以下的桩身进行处理，以减少负摩阻力",false,{"key":16,"text":17,"correct":18},"B","对于地表面大面积堆载的建筑物，采取预压等处理措施，减少堆载引起的地面下降",true,{"key":20,"text":21,"correct":18},"C","对于填土建筑场地，先填土，并保证填土的密实度，待填土地面沉降基本稳定后成桩",{"key":23,"text":24,"correct":18},"D","对于自重湿陷性黄土地基，采用强夯、挤密土桩等先行处理，以消除上部或全部土层的自重湿陷性","BCD","根据《建筑桩基技术规范》（JGJ 94—2008）第3. 4. 7条，可能出现负摩阻力的桩基，应对位于中性点以上的桩身可对表面进行处理，以减少负摩阻力。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]