[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981179":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981179,709,2,"多选题","按《水工建筑物抗震设计规范》(DL 5073—2000)土石坝上游坝坡抗震设计时，下列 ()选项是正确的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与水库最高蓄水位相组合",false,{"key":16,"text":17,"correct":18},"B","需要时与常遇的水位降落幅值组合",true,{"key":20,"text":21,"correct":18},"C","与坝坡抗震稳定性最不利的常遇水位组合",{"key":23,"text":24,"correct":18},"D","与水库正常蓄水位相组合","BCD","《水工建筑物抗震设计规范》（DL 5073—2000）第4.4. 1条规定，一般情况下，水工建筑物作抗震计算时的上游水位可采用正常蓄水位；多年调节水库经论证后可采用低于正常蓄水位的上游水位；根据第4. 4. 2?4. 4. 4条，可知BCD三项正确。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]