[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981172":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981172,709,2,"多选题","关于建筑抗震场地剪切波速的表述，下列说法哪些符合《建筑抗震设计规范》的规定? ( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","场地土等效剪切波速的计算深度取值与地基基础方案无关",true,{"key":16,"text":17,"correct":18},"B","计算等效剪切波速时，对剪切波速大于500m\u002Fs的土层，剪切波速取500m\u002Fs",false,{"key":20,"text":21,"correct":14},"C","在任何情况下，等效剪切波速计算深度不大于20m",{"key":23,"text":24,"correct":18},"D","场地土等效剪切波速的计算和场地覆盖层厚度无关","AC","参见《建筑抗震设计规范》（GB 50011 —2010)第4. 1. 4?4. 1. 5条规定。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]