[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981148":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981148,709,2,"多选题","基坑降水设计时，（ ）不正确。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","降水井宜沿基坑外缘采用封闭式布置",false,{"key":16,"text":17,"correct":18},"B","回灌井与降水井的距离不宜大于6m",true,{"key":20,"text":21,"correct":14},"C","降水引起的地面沉降可按分层总和法计算",{"key":23,"text":24,"correct":18},"D","沉降观测基准点应设在降水影响范围之内","BD","根据《建筑基坑支护技术规程》(JGJ 120—1999)第8.5.2条，回灌井与降水井的距离不宜小于6m；根据第3.8.4条，位移观测基准点数量不少于两点，且应设在影响范围以外。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]