[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981143":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981143,709,2,"多选题","既有建（构）筑物地基加固与基础托换主要从（ ）方面来考虑。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基础加宽、加深",true,{"key":16,"text":17,"correct":14},"B","地基加固",{"key":19,"text":20,"correct":14},"C","桩式托换",{"key":22,"text":23,"correct":24},"D","减小建筑物的承载力",false,"ABC","既有建（构）筑物地基加固与基础托换主要从三方面考虑：①通过将原基础加宽，减小作用在地基土上的接触压力。虽然地基土强度和压缩性没有改变，但单位面 积上荷载减小，地基土中附加应力水平减小，可使原地基满足建筑物对地基承载力和变形的要求。或者通过基础加深。虽未改变作用在地基土上的接触应力，但由于基础埋深加大，一是使基础置人较深的好土层，加大埋深，地基承载力通过深度修正也有所增加。②通过地基处理改良地基土体或改良部分地基土体，提高地基土体抗剪强度、 改善压缩性，以满足建筑物对地基承载力和变形的要求，常用如高压喷射注浆、压力注浆以及化学加固等技术。③在地基中设置墩基础或桩基础等竖向增强体，通过复合地基作用来满足建筑物对地基承载力和变形的要求，常用锚杆静压桩、树根桩或高压旋喷注浆等加固技术。有时可将上述几种技术综合应用。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]