[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981054":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981054,709,2,"多选题","根据《岩土工程勘察规范》(GB 50021——2001 )(2009年版）中载荷试验的技术要求，当( )时，可终止试验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承压板周边土出现明显侧向挤出或隆起",true,{"key":16,"text":17,"correct":14},"B","本级荷载沉降量大于前级荷载沉降量的5倍，曲线明显陡降",{"key":19,"text":20,"correct":14},"C","24h沉降速率不能达到相对稳定标准",{"key":22,"text":23,"correct":24},"D","总沉降量与承压板直径之比大于0.02或0.015",false,"ABC","《岩土工程勘察规范》（GB 50021-2001)(2009年版）第10. 2.3条第7款规定， 可终止试验的情况包括：①承压板周边土出现明显侧向挤出、明显隆起或径向裂缝持续发展；②本级荷载的沉降量大于前级荷载沉降量的5倍，荷载与沉降曲线出现明显陡降；③某级荷载下24小时沉降速率不能达到相对稳定标准；④总沉降量与承压板直径 (或宽度）之比超过0.06。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]