[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981042":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981042,709,2,"多选题","在房屋建筑和构筑物的岩土工程勘察详细勘察阶段的下述取样和测试要求中，错误的有( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","取样和进行原位测试的勘探孔数量不应少于勘探孔总数的1\u002F2",false,{"key":16,"text":17,"correct":18},"B","钻探取土试样孔的数量不应少于勘探孔总数的1\u002F2",true,{"key":20,"text":21,"correct":18},"C","对每个场地每一主要土层的原状土试样不应少于5件（组）",{"key":23,"text":24,"correct":14},"D","在地基主要持力层内，对厚度大于50cm的夹层或透镜体，应采取土试样或进行原位测试","BC","参见《岩土工程勘察规范》（GB 50021 —2001 )(2009年版）第4. 1.20条规定。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]