[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981022":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981022,709,2,"多选题","进行可行性研究的主要工作内容有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程勘察、设汁方案的确定",false,{"key":16,"text":17,"correct":14},"B","进行勘察、设计的招投标工作",{"key":19,"text":20,"correct":21},"C","资金、成本的研究",true,{"key":23,"text":24,"correct":21},"D","市场销售情况的研究","CD","可行性研究阶段主要r.作内容包括：①勘察任务、目的和要求；②拟建工程概况；③勘察方法和勘察工作量；④区域地质、地震概况；⑤场区地质、岩土和水文地质条件；⑥不良地质作用与地质灾害；⑦场地稳定性和适宜性的评价。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]