[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980974,709,1,"单选题","考虑预留建筑物有关部分之间的净空，采取相应的连接方法和施工顺序，需要预估建筑物在施工期间的地基变形值。一般非砂土的低压缩性黏土地基上的多层建筑物，在施工期间完成的沉降量，可认为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最终沉降鲁基本完成",false,{"key":16,"text":17,"correct":18},"B","已完成最终沉降量的50% ~ 80%",true,{"key":20,"text":21,"correct":14},"C","已完成最终沉降量的20%?50%",{"key":23,"text":24,"correct":14},"D","已完成最终沉降量的5% ~ 20%","根据《建筑地基基础设计规范》(GB 50007 —2002)第5. 3. 3条第2款，一般浅基础的建筑物在施工期间完成的沉降量：对于砂土可认为其最终沉降量已基本完成；对于低压缩黏性土可认为已完成最终沉降量的50% ~ 80% ;对于中压缩黏性土可认为巳完成20% ~50% ;对于高压缩黏性土可认为已完成5% ~20%。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]