[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980900,709,1,"单选题","在工程项目管理中，工程建设项目的投资和工程中的重大问题的决策由（ ）负责。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","施工单位","在工程项目管理中，设计单位负责设计文件等的质量、进度等；管理单位负责工程项目各阶段的监理工作，但不能决策，只能建议协助建设单位；施工单位负责工程各阶段的质量、工程施工管理等。工程建设项目的投资和工程中的重大问题的决策由建设单位负责。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]