[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980886,709,1,"单选题","依据《合同法》的有关条款，下列关于建设工程承包合同的做法，符合规定的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人可将应当由一个承包人完成的建设工程肢解成几个部分后分别发包给不同的承包人",false,{"key":16,"text":17,"correct":18},"B","承包人可经发包人同意将自己承包的部分工作交由第三人完成",true,{"key":20,"text":21,"correct":14},"C","分包单位可将其分包工程中的一部分再转包给有相应资质的施工单位",{"key":23,"text":24,"correct":14},"D","承包商可把全部承包工程分别分包给第三人","《合同法》中建设工程合同部分规定：①发包人不得将应当由一个承包人完成的建设工程肢解成若干部分发包给几个承包人；②承包人不得将其承包的全部建设工程转包给第三人或者将其承包的全部建设工程肢解以后以分包的名义分别转包给第三人；③禁止承包人将工程分包给不具备相应资质条件的单位。禁止分包单位将其承包的工程再分包。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]