[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},980878,709,1,"单选题","下列不属于标底内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标综合说明",true,{"key":16,"text":17,"correct":18},"B","工程量表",false,{"key":20,"text":21,"correct":18},"C","招标工程的直接费、间接费",{"key":23,"text":24,"correct":18},"D","主要材料的需要量","标底的内容有：①工程量表；②工程项目分部分项的单价；③招标工程的直接费、间接费及利润；④其他不可预见的费用估计；⑤招标工程项目的总造价，即标底总价；⑥主要材料（钢材、水泥及木材）的需用量；⑦招标工程的工期。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]