[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980866":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980866,709,1,"单选题","岩土工程治理预算费用中的其他直接费用不包括下列（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","夜间施工增加费",false,{"key":16,"text":17,"correct":14},"B","生产工具、用具使用费",{"key":19,"text":20,"correct":14},"C","特殊工种培训费",{"key":22,"text":23,"correct":24},"D","管理人员差旅交通费",true,"岩土工程治理预算费用中的其他直接费包括：①冬、雨季施工增加费；②夜间施工增加费；③材料二次搬运费；④仪器仪表使用费；⑤生产工具用具使用费；⑥检验试验费；⑦特殊工种培训费；⑧工程定位复测、工程点交、场地清理等费用；⑨特殊地区施工增加费。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]