[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},980860,709,1,"单选题","关于我国工程建设的基本程序，下列说法中错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","科学的建设程序应当坚持“先勘察、后设计、再施工”的原则",false,{"key":16,"text":17,"correct":14},"B","工程建设各项工作必须遵守先后次序的法则",{"key":19,"text":20,"correct":21},"C","建设程序分成若干阶段，这些阶段不是有严格的先后次序，根据工程建设项目的大小和重要性可以局部调整先后次序",true,{"key":23,"text":24,"correct":14},"D","可行性研究一定要在项目建议书批准后进行","C项，建设工程应按照严格的程序进行，即项目建议书；可行性研究；初步设计；技术设计；施工图设计；建设准备；建设实施；生产准备；竣工验收和后评价。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]