[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980855":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980855,709,1,"单选题","某岩土工程已知工程直接费10万元，间接费为15%，计划利润为10%，税金为4%， 其单位工程造价为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13. 00",false,{"key":16,"text":17,"correct":18},"B","13. 156",true,{"key":20,"text":21,"correct":14},"C","13. 25",{"key":23,"text":24,"correct":14},"D","14. 00","由已知可得，工程直接费为10万元；间接费为：10×15% =1.5(万元）；计划利润为：(10 + 1.5)×10% =1. 15(万元）；税金为：(10 + 1.5 + 1. 15)×4%=0.506(万元）；则单位工程造价为：10 + 1.5 +1.15 +0.506 = 13. 156(万元）。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]