[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},980853,709,1,"单选题","工程项目投资，一般是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","为获得预期利润而投放资本于国内或国外的企业行为",false,{"key":16,"text":17,"correct":14},"B","建设单位用于建筑和安装工程方面的投资",{"key":19,"text":20,"correct":21},"C","进行某项工程建设花费的全部投资",true,{"key":23,"text":24,"correct":14},"D","建设单位购置或自制达到固定资产标准的设备和新、扩建项目配置的首套工具及生 产家具所需的投资","建设项目投资是指在工程项目建设阶段所需要的全部费用的总和。生产性建设项目总投资包括建设投资、建设期利息和流动资金三部分；非生产性建设项目总投资包括建设投资和建设期利息两部分。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]