[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980842,709,1,"单选题","对工程建设勘察设计阶段执行强制性标准的情况实施监督的应当是下列（ ）种机构。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目规划审查机构",false,{"key":16,"text":17,"correct":18},"B","施工图设计文件审查机构",true,{"key":20,"text":21,"correct":14},"C","建设安全监督管理机构",{"key":23,"text":24,"correct":14},"D","工程质量监督机构","《实施工程建设强制性标准监督规定》第六条规定，建设项目规划审查机构应当对工程建设规划阶段执行强制性标准的情况实施监督；施工图设计文件审査单位应当对工程建设勘察、设计阶段执行强制性标准的情况实施监督；建筑安全监督管理机构应当对工程建设施工阶段执行施工安全强制性标准的情况实施监督；工程质量监督机构应当对工程建设施工、监理、验收等阶段执行强制性标准的情况实施监督。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]