[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},980837,709,1,"单选题","承包单位将承包的工程转包，且由于转包工程不符合规定的质量标准造成的损失，应按下列哪个选项承担赔偿责任？（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","只由承包单位承担赔偿责任",false,{"key":16,"text":17,"correct":14},"B","只由接受转包的单位承担赔偿责任",{"key":19,"text":20,"correct":21},"C","承包单位与接受转包的单位承担连带赔偿责任",true,{"key":23,"text":24,"correct":14},"D","建设单位、承包单位与接受转包的单位承担连带赔偿责任","《建筑法》第六十七条规定，承包单位将承包的工程转包的，或者违反本法规定进行分包的，责令改正，没收违法所得，并处罚款，可以责令停业整顿，降低资质等级；情节严重的，吊销资质证书。承包单位有前款规定的违法行为的，对因转包工程或者违法分包的工程不符合规定的质量标准造成的损失，与接受转包或者分包的单位承担连带赔偿责任。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]