[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980767,709,1,"单选题","勘探线和勘探点的布置应根据工程地质条件、地下水情况和滑坡形态确定。除沿主滑方向应布置勘探线外，在其两侧滑坡体外也应布置一定数量勘探线。勘探点间距不宜大于 ( )m,在滑坡体转折处和预计采取工程措施的地段，也应布置勘探点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","40",true,{"key":20,"text":21,"correct":14},"C","60",{"key":23,"text":24,"correct":14},"D","80","根据《岩土工程勘察规范》（GB 50021-2001）（2009年版)第5. 2. 4条，勘探线和勘探点的布置应根据工程地质条件、地下水情况和滑坡形态确定。除沿主滑方向应布置勘探线外，在其两侧滑坡体外也应布置一定数量勘探线。勘探点间距不宜大于40m，在滑坡体转折处和预计采取工程措施的地段，也应布置勘探点。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]