[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980761,709,1,"单选题","关于对土洞和塌陷的地基处理，下列措施不恰当的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地面截流",false,{"key":16,"text":17,"correct":14},"B","防渗",{"key":19,"text":20,"correct":14},"C","灌填岩溶通道",{"key":22,"text":23,"correct":24},"D","顶板塌落堵塞",true,"土洞和塌陷宜采用地表截流、防渗，堵漏、挖填灌填岩溶通道、通气降压等方法进行处理，同时采用梁板跨越；对重要建筑物应采用桩基或墩基。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]