[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980709,709,1,"单选题","下列关于土石坝的稳定计算工况的说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水库水位下降时的上游坝坡",false,{"key":16,"text":17,"correct":14},"B","稳定渗流期的下游坝坡",{"key":19,"text":20,"correct":14},"C","施工期（包括竣工时）的上下游坝坡",{"key":22,"text":23,"correct":24},"D","死水位时的上下游坝坡",true,"根据《碾压式土石坝设计规范》（SL 274—2001）第8.3. 1条，土石坝施工、建成、 蓄水和库水位降落的各个时期不同荷载下，应分别计算其稳定性，控制稳定的有施工期（包括竣工时）、稳定渗流期、水库水位降落期和正常运用遇地震四种工况，应计算的内容包括：①施工期的上、下游坝坡；②稳定渗流期的上、下游坝坡；③水库水位降落期的上游坝坡；④正常运用遇地震的上、下游坝坡。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]