[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980693,709,1,"单选题","在土石坝施工期用有效应力法计算坝坡稳定性时，如采用三轴仪测定无黏性土抗剪强度，应采用（ ）试验方法。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","慢剪",false,{"key":16,"text":17,"correct":14},"B","固结不排水剪测孔隙水压力",{"key":19,"text":20,"correct":14},"C","不排水剪测孔隙水压力",{"key":22,"text":23,"correct":24},"D","固结排水剪",true,"参见《碾压式土石坝设计规范》（SL 274—2001）附录D表D. 1. 1相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]