[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},980662,709,1,"单选题","下列（ ）工序为沉井施工的正确工序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平整场地，制作第一节沉井，拆除垫木，挖土下沉，接高井壁，沉井封底",true,{"key":16,"text":17,"correct":18},"B","平整场地，沉井封底，接高井壁，挖土下沉",false,{"key":20,"text":21,"correct":18},"C","平整场地，沉井封底，挖土下沉，接高井壁",{"key":23,"text":24,"correct":18},"D","平整场地，挖土下沉，沉井封底，接高井壁","参见《建筑地基基础工程施工质量验收规范》（GB 50202—2002）第7. 7节相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]