[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},980646,709,1,"单选题","混凝土预制桩在达到其设计强度的( )时方可起吊。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","70%",true,{"key":16,"text":17,"correct":18},"B","80%",false,{"key":20,"text":21,"correct":18},"C","90%",{"key":23,"text":24,"correct":18},"D","100%","根据《建筑桩基技术规范》(JGJ 94-2008)第7. 2. 1条第1款，混凝土预制桩达到设计强度的70%方可起吊，达到100%才能运输。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]