[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980607,709,1,"单选题","根据《建筑粧基技术规范》（JGJ94—2008),桩身有一定长度并嵌入风化基岩有一定深度的嵌岩桩，其单桩竖向承载力标准值应如何计算？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","桩周土总极限侧阻力",false,{"key":16,"text":17,"correct":18},"B","桩周土总极限侧阻力和桩嵌岩段总极限阻力",true,{"key":20,"text":21,"correct":14},"C","桩嵌岩段总极限阻力和总端阻力",{"key":23,"text":24,"correct":14},"D","桩周土总极限侧阻力和桩嵌岩段总极限阻力以及总端阻力","《建筑桩基技术规范》（JGJ94—2008）第5. 3. 9条规定，桩端置于完整、较完整基岩的嵌岩桩单桩竖向极限承载力，由桩周土总极限侧阻力和桩嵌岩段总极限阻力组成。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]