[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980580,709,1,"单选题","下列关于泥浆护壁灌注桩施工方法的叙述中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","灌注混凝土前应测量孔底沉渣厚度",false,{"key":16,"text":17,"correct":18},"B","在地下水位以下的地层中均可自行造浆护壁",true,{"key":20,"text":21,"correct":14},"C","水下灌注混凝土时，开始灌注混凝土前导管应设隔水栓",{"key":23,"text":24,"correct":14},"D","在混凝土灌注过程中严禁导管提出混凝土面并应连续施工","B项，根据《建筑桩基技术规范》(JGJ 94一2008)第6. 3. 1条规定，除能自行造浆的黏性土层外，均应制备泥浆。ACD三项均符合第6. 3. 9条、第6. 3. 29条、第6. 3. 30 条的相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]