[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980579,709,1,"单选题","对承受竖向荷载的混凝土预制桩，下列（ ）最有可能对主筋设置起控制作用。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","桩顶竖向荷载",false,{"key":16,"text":17,"correct":14},"B","桩侧阻力",{"key":19,"text":20,"correct":14},"C","沉桩对土的动阻力",{"key":22,"text":23,"correct":24},"D","起吊或运输时形成的弯矩",true,"根据《建筑桩基技术规范》(JCJ 94一2008)第4. 1. 6条规定，预制桩的桩身配筋应按吊运、打桩及桩在使用中受力等条件来计算确定。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]