[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},980513,709,1,"单选题","某土石坝坝址区地震烈度为8度，在10号孔深度为3m、6m和13m处测得剪切波速值分别为104m\u002Fs、217m\u002Fs和313m\u002Fs,该孔15m深度范围内土层2. 0m以内为回填黏性土层，2m至15m内为第四纪沉积粉砂细砂层，在工程正常运用时，该处地面淹没于水面以下，在进行地震液化初判时，下列（ ）选项是正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3m处的砂土层可能液化，6m和13m处的砂土层不液化",false,{"key":16,"text":17,"correct":14},"B","3m和6m处的砂土层可能液化，13m处的砂土层不液化",{"key":19,"text":20,"correct":21},"C","3m、6m、13m处的砂土层都可能液化",true,{"key":23,"text":24,"correct":14},"D","3m、6m、13m处的砂土层均不液化","根据《水利水电工程地质勘察规范》(GB 50487—2008)附录P第P. 0. 3条具体计算如下： 根据《中国地震动参数区划图》(GB 18306-2001)表D1，可知地震峰值加速度KH = 0. 2。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]