[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980500,709,1,"单选题","下列关于动态设计方法的描述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","动态设计即是不断地修改设计方案，使设计与边坡实际更好地结合",false,{"key":16,"text":17,"correct":14},"B","动态设计即是边勘察、边设计、边施工，及时选择新的设计方案以解决施工中的新问题",{"key":19,"text":20,"correct":14},"C","动态设计即是不能控制施工经费，如有必要应及时追加投资",{"key":22,"text":23,"correct":24},"D","动态设计即是一种根据现场地质情况和监测数据，验证地质结论及设计数据，从而对施工的安全性进行判断并及时修正施工方案的施工方法",true,"动态设计法是边坡工程设计的基本原则。一级边坡工程应采用动态设计法，应提出对施工方案的特殊要求和监测要求，应掌握施工现场的地质状况、施工情况和变形、应力监测的反馈信息，必要时对原设计进行校核、修改和补充。二级边坡工程宜采用动态设计法。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]