[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980484":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980484,709,1,"单选题","某建筑基坑采用单层预应力锚杆排桩支护体系，预应力锚杆进行张拉时，其控制应力不应超过锚杆杆体强度标准值的（ ）倍。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.6",false,{"key":16,"text":17,"correct":18},"B","0.75",true,{"key":20,"text":21,"correct":14},"C","0.8",{"key":23,"text":24,"correct":14},"D","0.95","根据《建筑基坑支护技术规程》（JGJ 120—1999）第4. 7. 3条第5款，锚杆的张拉与施加预应力（锁定）应符合的规定有：①锚固段强度大于15MPa并达到设计强度等级的75%后方可进行张拉；②锚杆张拉顺序应考虑对邻近锚杆的影响；③锚杆宜张拉至设计荷载的0. 9 ~ 1.0倍后，再按设计要求锁定；④锚杆张拉控制应力不应超过锚杆杆体强度标准值的0.75倍。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]