[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980482,709,1,"单选题","关于土钉墙的施工，下列叙述不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在坡面喷射混凝土支护之前应清除坡面虚土",false,{"key":16,"text":17,"correct":14},"B","坡面平整度的允许偏差宜为±20mm",{"key":19,"text":20,"correct":14},"C","基坑开挖和土钉墙施工应按设计要求自上而下分段分层进行",{"key":22,"text":23,"correct":24},"D","当上层土钉注浆体及喷射混凝土面层达到设计强度的75%后方可进行下层施工",true,"土钉墙是随基坑分层开挖形成的，以各个施工阶段的整体稳定性计算为标准决定是否可以进行下层施工。根据《建筑基坑支护技术规程》(JGJ 120—1999)第6.4.1条，上层土钉注浆体及喷射混凝土面层达到设计强度的70%后方可开挖下层土方及下层土钉施工。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]