[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980441,709,1,"单选题","拟用挤密桩法消除湿陷性黄土地基的湿陷性，当挤密桩直径d为0.4m，按三角形布桩时，桩孔中心距s采用1.0m，若桩径改为0. 45m，要求面积置换率m相同，此时桩孔中心距宜采用（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.08",false,{"key":16,"text":17,"correct":18},"B","1. 13",true,{"key":20,"text":21,"correct":14},"C","1.20",{"key":23,"text":24,"correct":14},"D","1.27","根据《建筑地基处理技术规范》（JGJ 79—2002）第7. 2. 8条，一根桩分担的处理地基面积的等效圆直径为：de=1.05s= 1. 05×1. 0 = 1. 05m；桩土面积置换率为：m =d2\u002Fd2e=0.42\u002F1.052=0.145；若桩径改为 0.45m，则 ，此时桩孔中心距为s′=d′e\u002F1.05=1.13m。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]