[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980433":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},980433,709,1,"单选题","在砂井堆载预压法中，通常预压荷载的大小宜为接近地基的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计荷载",true,{"key":16,"text":17,"correct":18},"B","极限荷载",false,{"key":20,"text":21,"correct":18},"C","临界荷载",{"key":23,"text":24,"correct":18},"D","标准荷载","预压荷载大小应根据设计要求确定，宜使预压荷载下受压土层各点的有效竖向应力大于建筑物荷载引起的相应点的附加应力。如果在建筑场地先加一个和上部建筑物的地基设计荷载相同的压力进行预压，使土层固结然后卸除荷载，再建造建筑物。这样，建筑物所引起的沉降即可大大减小。如果预压荷载大于建筑物地基设计荷载， 即所谓超载预压，则效果更好。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]