[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980430,709,1,"单选题","当砂井的平面布置采用等边三角形排列时，一根砂井的有效排水圆柱体的直径de和砂井间距s的关系按( ）公式确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","de= 1.50s",false,{"key":16,"text":17,"correct":18},"B","de=1.05s",true,{"key":20,"text":21,"correct":14},"C","de =1. 13s",{"key":23,"text":24,"correct":14},"D","de = 1.25s","参见《建筑地基处理技术规范》（JGJ 79—2002）第8. 2. 8条和第7. 2. 8条规定。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]