[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980376,709,1,"单选题","关于砂石桩施工顺序，下列哪一选项是错误的？（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","黏性土地基，从一侧向另一侧隔排进行",false,{"key":16,"text":17,"correct":18},"B","砂土地基，从中间向外围进行",true,{"key":20,"text":21,"correct":14},"C","黏性土地基，从中间向外围进行",{"key":23,"text":24,"correct":14},"D","临近既有建筑物，应自既有建筑物一侧向外进行","根据《建筑地基处理技术规范》（JGJ 79—2002）第8. 3. 6条，砂石桩的施工顺序： 对砂土地基宜从外围或两侧向中间进行，对黏性土地基宜从中间向外围或隔排施工；在既有建(构)筑物临近施工时，应背离建（构）筑物方向进行。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]