[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980335,709,1,"单选题","采取I级原状土样时应采用的方式为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","重锤少击",false,{"key":16,"text":17,"correct":14},"B","轻锤多击",{"key":19,"text":20,"correct":14},"C","间断静压",{"key":22,"text":23,"correct":24},"D","快速连续静压",true,"根据《原状土取样技术标准》（JGJ 89—1992）第3. 2. 2条规定，采取I级原状土样，应采取连续、快速的静压方式贯入取土器，贯入速度不小于0. 1m\u002Fs。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]