[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},980307,709,1,"单选题","污染土的承载力宜采用（ ）和其他原位测试确定，并进行污染土与未污染土的对比试验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","静力试验",false,{"key":16,"text":17,"correct":14},"B","剪切试验",{"key":19,"text":20,"correct":14},"C","旁压试验",{"key":22,"text":23,"correct":24},"D","载荷试验",true,"根据《岩土工程勘察规范》（GB 50021 —2001) (2009年版）第6. 10. 4条第4款, 对需要确定地基土工程性能的污染土，宜采用以原位测试为主的多种手段；当需要确定污染土地基承载力时，宜进行载荷试验。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]