[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},980274,709,1,"单选题","岩土工程初步勘察，当预定深度内有厚度较大、且分布均匀的坚实土层（如碎石土、 密实砂、老沉积土等）时，勘察孔深度应做的调整是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","除控制性孔达到规定深度外，一般性孔的深度可适当减少",true,{"key":16,"text":17,"correct":18},"B","所有钻孔均可酌情减少",false,{"key":20,"text":21,"correct":18},"C","为维护勘察合同的权威性，勘察资料的完整性，所有计划的孔深均不变",{"key":23,"text":24,"correct":18},"D","可酌情减少控制性钻孔的孔深和数量","根据《岩土工程勘察规范》（GB 50021—2001 )(2009年版）第4. 1. 8条规定，在预定深度内有厚度较大、且分布均匀的坚实土层（如碎石土、密实砂、老沉积土等）时，除控制性勘探孔达到规定深度外，一般勘探性孔的深度可适当减少。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]