[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980212,709,1,"单选题","根据《岩土工程勘察规范》（GB 50021—2001）（2009年版），在基坑工程的勘察中，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察深度宜为开挖深度的2?3倍",false,{"key":16,"text":17,"correct":18},"B","勘察的平面范围包括全部开挖边界内的范围",true,{"key":20,"text":21,"correct":14},"C","在深厚软土区，勘察深度和范围应适当扩大",{"key":23,"text":24,"correct":14},"D","复杂场地进行地下水治理时，应进专门的水文地质勘察","根据《岩土工程勘察规范》（GB 50021一2001）（2009年版）第4. 8.3条规定s基坑工程勘察的范围和深度应根据场地条件和设计要求确定。勘察深度宜为开挖深度的2 -3倍，在此深度内遇到坚硬黏性土、碎石土和沿展，可根据岩土类别和支护设计要求减少深度。勘察的平面范围宜超出开挖边界外开挖深度的2 ~3倍。在深厚软土区，勘察深度和范围应适当扩大，在开挖边界外，勘察手段以调丧研究、搜集已有资料为主，复杂场地和斜坡场地应布置适量的勘探点。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]