[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},980210,709,1,"单选题","根据《岩土工程勘察规范》（GB50021—2001) (2009年版）规定，核电厂的勘察不应包括的阶段是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步设计",false,{"key":16,"text":17,"correct":18},"B","详细设计",true,{"key":20,"text":21,"correct":14},"C","施工图设计",{"key":23,"text":24,"correct":14},"D","工程建造","《岩土工程勘察规范》(GB 50021—2001) (2009年版）第4. 6. 3条规定，核电厂岩土工程勘察可划分为初步可行性研究、可行性研究、初步设计、施工图设计和工程建造等五个勘察阶段。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]