[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},980167,709,1,"单选题","利用已有遥感资料进行工程地质测绘时，下列哪个选项的工作流程是正确的？（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","踏勘→初步解译→验证和成图",false,{"key":16,"text":17,"correct":14},"B","初步解译→详细解释→验证和成图",{"key":19,"text":20,"correct":21},"C","初步解译→踏勘和验证→成图",true,{"key":23,"text":24,"correct":14},"D","踏勘→初步解译→详细解释和成图","根据《岩土工程勘察规范》（GB 50021—2001) (2009年版）条文说明第8.0.7条， 利用已有遥感资料进行工程地质测绘时，在初步解译阶段，对航空相片或卫星相片进行系统的立体观测，对地貌和第四纪地质进行解译，划分松散沉积物与基岩的界线，进行初步构造解译等。第二阶段是野外踏勘和验证。核实各典型地质体在照片上的位置，并选择一些地段进行重点研究，作实测地质剖面和采集必要的标本。最后阶段是成图，将解译资料，野外验证资料和其他方法取得的资料，集中转绘到地形底图上，然后进行图面结构的分析。如有不合理现象，要进行修正，重新解译或到野外复验。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业知识","建筑工程",0]