[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-980031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},980031,707,1,"单选题","原位测试技术通常在岩土工程勘察的哪个阶段采用?",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工勘察",false,{"key":16,"text":17,"correct":14},"B","初步勘察",{"key":19,"text":20,"correct":21},"C","详细勘察",true,{"key":23,"text":24,"correct":14},"D","选址勘察","提示:原位测试应以测绘、勘探为基础，并为施工提供资料。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]