[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},979832,707,1,"单选题","为缩短排水固结处理地基的工期，最有效的措施是下列哪一项？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","用高能量机械压实",false,{"key":16,"text":17,"correct":14},"B","加大地面预压荷重",{"key":19,"text":20,"correct":21},"C","设置水平向排水砂层",true,{"key":23,"text":24,"correct":14},"D","减小地面预压荷重","提示:在地基中设置水平向排水砂层，增加了水平向排水通道，缩短了渗径，可以加速地基固结。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]