[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},979350,707,1,"单选题","双代号网络图中，某非关键工作被拖延了2d，其自由时差为1d，总时差为3d，则会出现下列中哪项结果？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","后续工作最早可能开始时间不变",false,{"key":16,"text":17,"correct":18},"B","将改变后续工作最早可能开始时间",true,{"key":20,"text":21,"correct":14},"C","会影响总工期",{"key":23,"text":24,"correct":14},"D","要改变紧前工作的最早可能开始时间","提示:某非关键工作被拖延的天数，当不超过其自由时差时，其后续工作最早可能开始时间不变；当超过其自由时差，但没超过其总时差，将改变后续工作最早可能开始时间，但是，不会影响总工期。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]