[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},979349,707,1,"单选题","双代号网络图中引入虚工作的一个原因是为了表达什么？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","表达不需消耗时间的工作",false,{"key":16,"text":17,"correct":14},"B","表达不需消耗资源的工作",{"key":19,"text":20,"correct":21},"C","表达工作间的逻辑关系",true,{"key":23,"text":24,"correct":14},"D","节省箭线和节点","提示:双代号网络图中的虚工作，一个重要的作用就是正确表达工作间的逻辑关系。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]