[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979347":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},979347,707,1,"单选题","某项工作有两项紧后工作D和 E，D的最迟完成时间是20d，持续时间是13d；E的最迟完成时间是15d，持续时间是10d。则本工作的最迟完成时间是：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20d",false,{"key":16,"text":17,"correct":14},"B","15d",{"key":19,"text":20,"correct":21},"C","5d",true,{"key":23,"text":24,"correct":14},"D","13d","提示:本工作的最迟完成时间等于各紧后工作最迟开始时间中取小值，经计算得:D的最迟开始时间的最迟完成时间-D的持续时间=20 - 13 = 7d，E的最迟开始时间=E的最迟完成时间-E的持续时间=15-10=5d，本工作的最迟完成时间为7与5的小值，等于5d。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]