[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},979345,707,1,"单选题","某工程双代号网络图如图所示，工作①→③的局部时差应为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1d",false,{"key":16,"text":17,"correct":18},"B","2d",true,{"key":20,"text":21,"correct":14},"C","3d",{"key":23,"text":24,"correct":14},"D","4d","提示:经计算，工作①→③的紧后工作③→④的最早开始时间是7d，工作①→③的最早完成时间为5d。工作①→③的局部时差=紧后工作的最早开始时间-本工作的最早完成时间=7-5 = 2d。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]